PDG was tasked with analyzing single points of failure within
the their existing infrastructure and design and to construct a new enterprise
data center facility and support space within an existing warehouse space at this
paint and coating manufacturing company's Santa Ana, California corporate campus.
Facilities Provided: 2,500 square foot consolidated
enterprise data center, 1,000 square foot Network Operations Center on raised
computer floor and N+1 redundancy for UPS, A/C and PDUs. The support facilities
included data center expansion area and a hardware setup area adjacent to the
data center. Total Construction Cost:
$2,000,000 USD |